Following application of the Questar-P methodology, inspection, monitoring and mitigation methods were recommended in order to provide future assurance of facility integrity. This, in effect, extended inspection intervals and reduced the number of costly internal vessel interventions by focusing inspection resource more efficiently.
On a like-for-like basis, forecast inspection expenditure over the five year period 2004 to 2008 was forecast to be approximately £510,000 (GBP); this being a 47% expenditure reduction.
In addition to these predicted savings in expenditure, a fully auditable inspection rationale was provided to underpin the inspection regime set in place.
|